Completion of the State Primary Music School in Ostrowiec Świętokrzyski

We have completed the extension of the State Primary Music School in Ostrowiec Świętokrzyski. The realisation of this investment consisted of several stages.

The first stage included the shell and closed state, i.e. the building was constructed with windows, doors and the necessary installations.

Following the completion of the first stage, a foundation act was ceremoniously laid. The event was attended by representatives of local authorities and the Ministry of Culture. As part of the ceremony, a concert was held in the chamber hall, featuring performances by young artists.

The second phase included the scope of finishing work on the façade, rooms, door carpentry and landscaping. We carried out the elevation of the building, connection and installation works, landscaping and finishing works.

Stage III of the task, closing the whole undertaking, was the extension of the School to include a concert hall with facilities and the construction of internal installations, such as water and sewage systems, central heating, mechanical ventilation, air conditioning, electrical, teletechnical and low-current systems, as well as technical infrastructure. Phase III included, among other things, the fitting out of the mobile stage, equipping the building with an electro-acoustic system and stage lighting, the installation of seats, and finishing work on the heating, lighting, mechanical ventilation, air conditioning, electrical, teletechnical and low-current installations.

The concert hall will accommodate 265 people and a recording studio with facilities for artists. There will be a room for the orchestra, a rhythm room, two rooms for the percussion class, and guest rooms for large competitions.